| Location: |
Houston, Texas |
| Completed: |
3/31/2013
|
| Square Feet: |
575,000 |
| Owner: |
Aldine Independent School District |
| Architect: |
Morris Architects
|
| The new high school is a 435,000 sf two story complex consisting of classrooms, practice and competition gymnasiums, auditorium, auto shop, pre vet classroom, woodshop, practice and competition baseball and softball fields, practice football field, tennis courts, practice soccer field, band room, natatorium, Junior ROTC shooting range, science labs, pre-nursing clinic, cosmotology lab, nurses station and administrative offices. Completion of high school is March 2012. The new 9th grade center is 140,000 sf single story complex consisting of classrooms, administrative offices, practice and competition basketball courts, science labs, nurses station, cafetorium and kitchen. This project will be completed in March 2013. |
|